Additional Finance

Additional Financing under NCRMP Phase-I

NCRMP (Additional Financing) has been formulated to fill up the infrastructural gaps observed during cyclone Phailin by creating additional infrastructure . The total Outlay under Additional Financing is Rs 835Cr. which includes Rs 645.50Cr credit from the
World Bank and 25% contribution by State Governments totalling Rs 189.50Cr under Component-B on the same lines as in the NCRMP Ph-I.

Government of India has approved Additional Financing in July, 2015 for the States of AP and Odisha with closure by October 2017

Physical Outlay Under NCRMP(AF)

Sub-Component Andhra Pradesh Odisha
Physical Outlay Physical Outlay
Multi Purpose Cyclone Shelters(MPCS) 84 162
Roads 75/119.79 kms 100/85 kms
Bridges 15 Nil
Total 174/119.79 kms 262/85 kms

 

Financial Outlay Under NCRMP(AF)

(Rs in Crores)

Component Andhra Pradesh Odisha
‘B’ – Cyclone Risk Mitigation Infrastructure 357.50 400.00
‘D’ – Implementation Status 37.50 40.00
Total 395.00

(With World Bank Share of Rs 305.50Cr)

440.00

(With World Bank Share of Rs 340.00Cr)

 
Physical Progress and Achievements: till March.2016
Andhra Pradesh

 

SINo. Components To be constructed Completed Under Execution Remarks
1 Construction of MPCSs 84 76 8 MPCSs are under advanced stage of tender finalization & remaining 7 bridges are under various stages of tendering/estimation
2 Roads (No/Kms) 75(119.79 kms) 8 67
3 Bridges 12 5
  Total 171(119.79 kms) 8 148

Odisha

SINo. Components To be constructed Completed Under Execution Remarks
1 Construction of MPCSs 162 23 139 All the works stand awarded.
2 Roads (No/Kms) 100/85 kms 38 62
  Total 262/85 kms 61 201

An amount of Rs. 366.72Cr.(including GoI & State share) has been released & an expenditure of Rs. 243.68Cr. ( GoI & State ) has been incurred till March 2016 under Additional Financing.