NCRMP Phase-II
Government of India approved Phase-II of NCRMP in July,2015 for five years up to September, 2022 covering States of Goa, Gujarat, Karnataka, Kerala, Maharashtra and West Bengal at an Outlay of Rs 2361.35 Cr with World Bank assistance amounting to Rs1881.20Cr. The remaining amount of Rs 480.15Cr. is being contributed by State Governments as their share.
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Technical bids under evaluation. |
Maharashtra | : | Technical bids under evaluation. |
Karnataka | : | SPIU will re-tender EWDS after getting approval of World Bank. |
Kerala | : | Tender floated and Pre bid meeting is scheduled on 17/09/2019. Last date of submission of bids is 01/10/2019. |
Gujarat | : | Pre bid meeting held on 03/09/2019. Last date of bid submission is 18/09/2019. |
West Bengal | : | SPIU to comply the observations of the World Bank and submit bid document for approval of the World Bank. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | (a). 06 MPCS under construction.
(b). 01 MPCS work suspended. (c). 04 Tender under evaluation. (d). Tracing of underground cables completed in 01 MPCS. |
Road (30 Kms) : | (a). Dropped keeping in view sufficiency of existing network. | ||
Saline Embankment (8.26 Km) : | (a). DPR incorporating EIA/ SIA report under review with World Bank. | ||
Underground Cabling (98 Km) : | (a). Site identified at Anjuna Beach.
(b). DPR under review with SPIU for compliance of observations of World Bank. (c). Financial Bid to be opened on 13th September,2019. |
||
2. | Gujarat | MPCS (95 No.) : | (a). 26 completed
(b). 66 under construction (c). 3 re-tenders to be issued by September, 2019 |
Road (157 Km) : | (a). 134 km completed.
(b). 23 km under construction and likely to be completed by 30th September, 2019. |
||
Underground Cabling (UGC) (430 Km) : | (a). Financial bid evaluation completed and report under review. Likely to be awarded by September, 2019. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 02 MPCS completed
(b). 09 under construction. |
Roads (48 Kms) : | (a). 45 km completed (b). 3 Km in progress. |
||
Bridges (2 Nos.) : | (a).RFP to be floated by March.2019.
(b). Revised DPR incorporating EIA/SIA report under review with SPIU to be shared with World Bank with land details shortly. |
||
Saline Embankment (7 Kms) : | (a) Revised DPR for Manikatte Saline Embankment under review with SPIU for compliance of World Bank observations.
(b) Bid to be open on 13.09.2019 |
||
4. | Kerala | MPCS (14 No.): | (a). all 14 MPCS under construction. 60% work has been completed. |
5. | Maharashtra | MPCS (11 Nos.) : | (a). Tender for 11 MPCS opened on 20.08.2019 and tender under evaluation. |
Saline Embankment (29.55 Km.) : | (a) Tender opened on 22.08.2019 and under evaluation. | ||
Underground Cabling (471 Kms.) : | (a). Alibagh Town work under execution.
(b). Ratnagiri and Satpati packages to be Award soon after getting CRC clearance. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 141 MPCS completed.
(b). Work in progress in 05 MPCS and likely to be completed by 31st October 2019. |
Underground Cabling (515 Kms) : | (a). Tender for one package (500 km) awarded – Package 1A Awarded.
(b). Minor package (15km) –Package 1B, 1C clubbed & approval of World Bank awaited for entrusting the work to WBSEDCL. |
134 km of Road and 26 MPCS completed in Gujarat,45 km of Roads completed in Karnataka and 141 MPCS completed in West Bengal.
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation ((BME) of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Technical bids under evaluation. |
Maharashtra | : | Technical bids under evaluation. |
Karnataka | : | Tender floated to be open on 31.10.2019. |
Kerala | : | Tender floated to be open on 22.10.2019. |
Gujarat | : | Pre bid meeting held on 03/09/2019. Last date of bid submission is 14.10.2019. |
West Bengal | : | SPIU to comply the observations of the World Bank and submit bid document for approval of the World Bank. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | (a). 06 MPCS under construction.
(b). 01 MPCS work suspended. (c). 04 Tender under evaluation. (d). Tracing of underground cables completed in 01 MPCS. |
Road (30 Kms) : | (a). Dropped keeping in view sufficiency of existing network. | ||
Saline Embankment (8.26 Km) : | (a). DPR incorporating EIA/ SIA report under review with World Bank. | ||
Underground Cabling (98 Km) : | (a). Site identified at Anjuna Beach.
(b). DPR under review with SPIU for compliance of observations of World Bank. (c). Financial Bid to be opened on 13th September,2019. |
||
2. | Gujarat | MPCS (95 No.) : | (a). 26 completed
(b). 66 under construction (c). 3 re-tenders to be issued by September, 2019 (d). Present status of MPCS Click here |
Road (157 Km) : | (a). 134 km completed.
(b). 23 km under construction and likely to be completed by 30th September, 2019. |
||
Underground Cabling (UGC) (430 Km) : | (a). Financial bid evaluation completed and report under review. Likely to be awarded by September, 2019. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 02 MPCS completed
(b). 09 under construction. |
Roads (48 Kms) : | (a). 46 km completed (b). 2 Km in progress. |
||
Bridges (2 Nos.) : | (a). RFP to be floated by March.2019.
(b). Revised DPR incorporating EIA/SIA report under review with SPIU to be shared with World Bank with land details shortly. |
||
Saline Embankment (7 Kms) : | (a) Tender floated to be open on 12.10.2019.
(b) Bid to be open on 13.09.2019 |
||
4. | Kerala | MPCS (14 No.): | (a). all 14 MPCS under construction. 60% work has been completed. |
5. | Maharashtra | MPCS (11 Nos.) : | (a). Under award stage. |
Saline Embankment (29.55 Km.) : | (a) Under award stage. | ||
Underground Cabling (471 Kms.) : | (a). Alibagh Town work under execution.
(b). Ratnagiri and Satpati packages to be Award soon after getting CRC clearance. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 141 MPCS completed.
(b). Work in progress in 05 MPCS and likely to be completed by 31st October 2019. |
Underground Cabling (515 Kms) : | (a). Tender for one package (500 km) awarded – Package 1A Awarded.
(b). Minor package (15km) –Package 1B, 1C clubbed & approval of World Bank awaited for entrusting the work to WBSEDCL. |
134 km of Road and 26 MPCS completed in Gujarat,45 km of Roads completed in Karnataka and 141 MPCS completed in West Bengal.
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020. |
Karnataka | : | Work Awarded on 4th November 2020 to M/s BECIL Ltd. |
Kerala | : | Work awarded on 4th December 2020 to M/s CMS Computer Pvt. Ltd. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 01 MPCS Completed.
(b). 11 MPCS Under Execution. |
Underground Cabling (98 Km) : | 80% UGC work has been completed. 20% under execution. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 34 completed
(b). 42 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 08 MPCS completed
(b). 03 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 40% work has been completed and remaining 60% are under execution. | ||
Saline Embankment (7.8 Kms) : | 35% work has been completed and remaining 65% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 07 MPCS completed.
(b). 10 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a) Under execution. |
Underground Cabling (471 Kms.) : | (a). 144 KM Completed.
(b). 327 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed.
(b). 27.54 KM Under execution. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020. |
Karnataka | : | Work order issued on 16th March 2021 to M/s BECIL Ltd. |
Kerala | : | Work order issued on 22nd January 2021 to M/s CMS Computer Pvt. Ltd. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 01 MPCS Completed.
(b). 11 MPCS Under Execution. |
Underground Cabling (315 Km) : | 85% UGC work has been completed. 15% under execution. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 34 completed
(b). 42 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 08 MPCS completed
(b). 03 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 46% work has been completed and remaining 54% are under execution. | ||
Saline Embankment (7.8 Kms) : | 52% work has been completed and remaining 48% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 11 MPCS completed.
(b). 06 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a)41.08% work has been completed and remaining 58.92% are under execution.. |
Underground Cabling (471 Kms.) : | (a). 175.3 KM Completed.
(b). 295.7 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed.
(b). 27.54 KM Under execution. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020. |
Karnataka | : | Work order issued on 16th March 2021 to M/s BECIL Ltd. |
Kerala | : | Work order issued on 22nd January 2021 to M/s CMS Computer Pvt. Ltd. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 01 MPCS Completed.
(b). 11 MPCS Under Execution. |
Underground Cabling (315 Km) : | 87% UGC work has been completed. 13% under execution. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 54 completed
(b). 22 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 08 MPCS completed
(b). 03 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 75% work has been completed and remaining 25% are under execution. | ||
Saline Embankment (7.8 Kms) : | 52% work has been completed and remaining 48% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 11 MPCS completed.
(b). 06 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a)41.64% work has been completed and remaining 58.36% are under execution.. |
Underground Cabling (471 Kms.) : | (a). 196.11 KM Completed.
(b). 274.89 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020. |
Karnataka | : | Work order issued on 16th March 2021 to M/s BECIL Ltd. |
Kerala | : | Work order issued on 22nd January 2021 to M/s CMS Computer Pvt. Ltd. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 01 MPCS Completed.
(b). 11 MPCS Under Execution. |
Underground Cabling (315 Km) : | 283.5 KM UGC work has been completed. 31.5 KM under execution. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 56 completed
(b). 20 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 08 MPCS completed
(b). 03 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 75% work has been completed and remaining 25% are under execution. | ||
Saline Embankment (7.8 Kms) : | 56% work has been completed and remaining 44% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 11 MPCS completed.
(b). 06 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a)41.64% work has been completed and remaining 58.36% are under execution.. |
Underground Cabling (471 Kms.) : | (a). 196.11 KM Completed.
(b). 274.89 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020 and 10% work completed and 90% under execution. |
Karnataka | : | Work order issued on 16th March 2021 to M/s BECIL Ltd. and 10% work completed and 90% under execution. |
Kerala | : | Work order issued on 22nd January 2021 to M/s CMS Computer Pvt. Ltd. and 50% work completed and 50% under execution. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 03 MPCS Completed.
(b). 09 MPCS Under Execution. |
Underground Cabling (315 Km) : | 299.25 KM UGC work has been completed. 15.75 KM under execution. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 59 completed
(b). 17 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 09 MPCS completed
(b). 02 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 75% work has been completed and remaining 25% are under execution. | ||
Saline Embankment (7.8 Kms) : | 56% work has been completed and remaining 44% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 11 MPCS completed.
(b). 06 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a)49.28% work has been completed and remaining 50.72% are under execution.. |
Underground Cabling (471 Kms.) : | (a). 219.44 KM Completed.
(b). 251.56 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020 and 30% work completed and 70% under execution. |
Karnataka | : | Work order issued on 16th March 2021 to M/s BECIL Ltd. and 10% work completed and 90% under execution. |
Kerala | : | Work order issued on 22nd January 2021 to M/s CMS Computer Pvt. Ltd. and 72% work completed and 28% under execution. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 05 MPCS Completed.
(b). 07 MPCS Under Execution. |
Underground Cabling (315 Km) : | 315 KM UGC work has been completed. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 66 completed
(b). 10 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (11 Nos.) : | (a). 09 MPCS completed
(b). 02 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 75% work has been completed and remaining 25% are under execution. | ||
Saline Embankment (7.8 Kms) : | 63% work has been completed and remaining 37% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 11 MPCS completed.
(b). 06 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a)68.18% work has been completed and remaining 31.82% are under execution.. |
Underground Cabling (471 Kms.) : | (a). 290.47 KM Completed.
(b). 180.53 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020 and 45% work completed and 55% under execution. |
Karnataka | : | Work order issued on 16th March 2021 to M/s BECIL Ltd. and 15% work completed and 85% under execution. |
Kerala | : | Work order issued on 22nd January 2021 to M/s CMS Computer Pvt. Ltd. and 72% work completed and 28% under execution. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 05 MPCS Completed.
(b). 07 MPCS Under Execution. |
Underground Cabling (315 Km) : | 315 KM UGC work has been completed. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 70 completed
(b). 6 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (10 Nos.) : | (a). 09 MPCS completed
(b). 01 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 75% work has been completed and remaining 25% are under execution. | ||
Saline Embankment (7.8 Kms) : | 63% work has been completed and remaining 37% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 13 MPCS completed.
(b). 04 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a)76.33% work has been completed and remaining 23.67% are under execution.. |
Underground Cabling (471 Kms.) : | (a). 340 KM Completed.
(b). 131 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|
(i) Component A (EWDS):
(a). States of Goa, Maharashtra, Karnataka and Kerala have finalized TCIL as Knowledge Partner/ Consultant to provide assistance for implementation of EWDS. Gujarat and West Bengal has engaged KPMG and Pricewaterhouse Coopers Pvt. Ltd. as Knowledge Partner respectively.
(b).
Goa | : | Work awarded to M/s BIPS System Ltd. on 12th March 2020 and 45% work completed and 55% under execution. |
Karnataka | : | Work order issued on 16th March 2021 to M/s BECIL Ltd. and 15% work completed and 85% under execution. |
Kerala | : | Work order issued on 22nd January 2021 to M/s CMS Computer Pvt. Ltd. and 72% work completed and 28% under execution. |
(ii) Component B (Infrastructure)
SI No | State | Items | Status |
1. | Goa | MPCS(12 Nos.) : | a). 10 MPCS Completed.
(b). 02 MPCS Under Execution. |
Underground Cabling (315 Km) : | 315 KM UGC work has been completed. | ||
2. | Gujarat | MPCS (76 No.) : | (a). 70 completed
(b). 6 under construction. |
Road (157 Km) : | (a). 157 km completed. | ||
3. | Karnataka | MPCS (10 Nos.) : | (a). 09 MPCS completed
(b). 01 under construction. |
Roads (48 Kms) : | (a). 48 km completed. | ||
Bridges (2 Nos.) : | 84% work has been completed and remaining 16% are under execution. | ||
Saline Embankment (7.8 Kms) : | 72% work has been completed and remaining 28% are under execution. | ||
4. | Kerala | MPCS (17 No.): | (a). 13 MPCS completed.
(b). 04 MPCS under construction. |
5. | Maharashtra | Saline Embankment (22.26 Km.) : | (a)84.71% work has been completed and remaining 15.29% are under execution.. |
Underground Cabling (471 Kms.) : | (a). 368.59 KM Completed.
(b). 102.41 KM under execution. |
||
6. | West Bengal | MPCS (146 Nos.) : | (a). 146 MPCS completed. |
Underground Cabling (500 Kms) : | (a). 472.46 KM Completed. |
iii) Component C: Technical Assistance and Capacity Building
I. | Multi- Hazard Risk Assessment (MHRA) Study |
|
II. | National Seismic Risk Mitigation Project (NSRMP) |
|
III. | Hydro-meteorological Resilience Action Plan (HmRAP): |
|
IV. | Benefit Monitoring & Evaluation (BME of Phase II) |
|
V. | Designing of Comprehensive Multi hazard Risk Financing Strategy (CMhRFS) under of Phase II) |
|